創建世久營造 奠定經營基礎

營業項目

營業項目

工程項目

地工技術

台中長榮桂冠大飯店擋土樁工程(1989)

Steel pile driven work for Evergreen Laurel Hotel (Taichung City)

澎湖馬公港碼頭擴建鋼管樁海上打設工程(1991)

Steel pipe pile drive work wharf expansion project (Penghu Island)

台塑麥寮六輕台塑重工廠房動力夯實地盤改良工程(1994)

Dynamic Consolidation ground improvement project for FPG 6th Refining Plant.

Taipei 101基礎連壁工程施工(1998)

Diaphragm wall work for “Taipei 101”

中油大樓基礎連續壁工程(1998)

Diaphragm wall work for CPC Headquarter office building.

新光三越信義新天地基礎連續壁工程(2001)

Diaphragm wall work for Shin Kong Mitsukoshi Xinyi Place Mall

中美和台中港地質改良礫石樁工程(2001)

Stone column ground improvement work for CAPCO #6 PTA Plant.

信義之星基礎連續壁工程施工(2001)

Diaphragm wall work for Xinyi star building.

國家藝術館基礎連續壁工程施工(2001)

Diaphragm wall work for National gallery of Art building.

財神酒店拆除、連續壁及基樁工程(2002)

Diaphragm wall & piling work for The God of Wealth hotel building.

台北統一企業國際大樓基樁連續壁工程(2002)

Diaphragm wall work for President Group Headquarter building.

宏盛帝寶基礎連續壁工程(2002)

Diaphragm wall work for Hung Sheng Depo building

南港專案南港車站先期連續壁工程(2003)

Diaphragm wall work for Nangang Railway Station.

高雄捷運CR3區段標R8車站連續壁工程(2005)

Diaphragm wall work for KRTC MRT R8 Sanduo Shopping District Station.

北宜高速公路雪山隧道防水層鋪設工程(2006)

Membrane installation waterproofing work for Hsuehshan Tunnel.

台北港貨儲運中心新建工程地質改良工程(2007)

Dynamic Consolidation ground improvement work for Taipei Harbor containers yard.

高雄左營自治新村改建支撐背拉地錨工程(2008)

Tie back system earth anchor installation work for Kaohsiung Zuoying autonomous village.

機場捷運A8站聯合大樓地下連續壁工程(2009)

Diaphragm wall work for Airport Link A8 joint development building.

台肥台中廠廠區動力夯實地質改良工程(2009)

Dynamic Consolidation ground improvement work for Taiwan Fertilizer Plant.

清 大宜蘭園區公共設施工程垂直排水帶打設(2011)

Vertical Drain installation work for National Tsing Hua University Yilan school Zone.

CA441A標台北車站特定專用區C1及D1東半街廓連續壁工程(2013)

Airport link C1&D1 Diaphragm wall project

板橋浮洲合宜住宅

Diaphragm wall work for New Taipei City Desirable residential building.

大林石化油品儲運中心第一期地質改良統包工程

Cpc.Dalin Peroleum Conservation and Transportation Center Soil Improvement Project (Turnkey Project) Phase I.

第三座液化天然氣接收站儲槽興建統包工程地質改良工作

ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING WORKS FOR LNG STORAGE TANKS OF CPC THIRD TERMINLA L10502 PROJECT